Filters
Question type

The spending variance for laundry costs for the month is:


A) $5,080 F
B) $5,080 U
C) $5,800 U
D) $5,800 F

E) B) and D)
F) All of the above

Correct Answer

verifed

verified

The labor efficiency variance for March is:


A) $3,040 U
B) $3,685 U
C) $3,685 F
D) $3,040 F

E) All of the above
F) B) and C)

Correct Answer

verifed

verified

If variable manufacturing overhead is applied based on direct labor-hours, it is impossible to have a favorable labor rate variance and unfavorable variable overhead rate variance for the same period.

A) True
B) False

Correct Answer

verifed

verified

The labor efficiency variance for July is:


A) $2,090 F
B) $2,166 U
C) $2,090 U
D) $2,166 F

E) A) and B)
F) None of the above

Correct Answer

verifed

verified

What is ChocO's variable overhead efficiency variance?


A) $7,260 Unfavorable
B) $10,560 Favorable
C) $31,240 Unfavorable
D) $39,050 Unfavorable

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

The total standard cost per unit is closest to:


A) $55.03 per unit
B) $43.45 per unit
C) $56.52 per unit
D) $44.97 per unit

E) A) and B)
F) C) and D)

Correct Answer

verifed

verified

The materials quantity variance for September is:


A) $2,170 U
B) $2,232 U
C) $2,170 F
D) $2,232 F

E) A) and C)
F) A) and B)

Correct Answer

verifed

verified

The total variable cost at the activity level of 9,300 patient-visits per month should be:


A) $114,390
B) $149,730
C) $102,090
D) $133,630

E) B) and C)
F) A) and D)

Correct Answer

verifed

verified

The spending variance for "Employee salaries and wages" for March would have been closest to:


A) $3,300 U
B) $3,300 F
C) $300 U
D) $300 F

E) B) and C)
F) A) and D)

Correct Answer

verifed

verified

The total fixed cost at the activity level of 5,500 guest-days per month should be:


A) $139,700
B) $190,920
C) $244,200
D) $109,220

E) B) and C)
F) A) and B)

Correct Answer

verifed

verified

The materials price variance for July is:


A) $2,100 U
B) $2,420 F
C) $2,100 F
D) $2,420 U

E) A) and C)
F) All of the above

Correct Answer

verifed

verified

The occupancy expenses in the flexible budget for September would be closest to:


A) $13,215
B) $12,808
C) $13,583
D) $12,880

E) A) and B)
F) All of the above

Correct Answer

verifed

verified

Krizun Industries makes heavy construction equipment.The standard for a particular crane calls for 20 direct labor-hours at $24 per direct labor-hour.During a recent period 875 cranes were made.The labor efficiency variance was $1,200 Unfavorable.How many actual direct labor-hours were worked?


A) 17,600 direct labor-hours
B) 17,450 direct labor-hours
C) 17,500 direct labor-hours
D) 17,550 direct labor-hours

E) C) and D)
F) B) and C)

Correct Answer

verifed

verified

Warp Manufacturing Corporation uses a standard cost system for the production of its ski lift chairs.Warp uses machine-hours as an overhead base.The variable manufacturing overhead standards for each chair are 1.2 machine-hours at a standard cost of $18 per hour. During the month of September, Warp incurred 34,000 machine-hours in the production of 32,000 ski lift chairs.The total variable manufacturing overhead cost was $649,400.What is Warp's variable overhead rate variance for September?


A) $37,400 Unfavorable
B) $41,800 Favorable
C) $79,200 Favorable
D) $84,040 Favorable

E) B) and D)
F) A) and C)

Correct Answer

verifed

verified

When more hours of labor time are necessary to complete a job than the standard allows, the labor efficiency variance is unfavorable.

A) True
B) False

Correct Answer

verifed

verified

The amount shown for revenue in the planning budget for March would have been closest to:


A) $126,000
B) $140,400
C) $142,435
D) $124,200

E) C) and D)
F) All of the above

Correct Answer

verifed

verified

Pittman Framing's cost formula for its supplies cost is $1,150 per month plus $11 per frame.For the month of November, the company planned for activity of 789 frames, but the actual level of activity was 792 frames.The actual supplies cost for the month was $9,480.The spending variance for supplies cost in November would be closest to:


A) $349 F
B) $382 U
C) $382 F
D) $349 U

E) A) and B)
F) None of the above

Correct Answer

verifed

verified

The labor efficiency variance for July is:


A) $450 U
B) $423 F
C) $423 U
D) $450 F

E) A) and D)
F) None of the above

Correct Answer

verifed

verified

The following standards for variable manufacturing overhead have been established for a company that makes only one product: The following standards for variable manufacturing overhead have been established for a company that makes only one product:   The following data pertain to operations for the last month:   What is the variable overhead efficiency variance for the month? A) $15,550 U B) $15,200 U C) $16,530 U D) $980 F The following data pertain to operations for the last month: The following standards for variable manufacturing overhead have been established for a company that makes only one product:   The following data pertain to operations for the last month:   What is the variable overhead efficiency variance for the month? A) $15,550 U B) $15,200 U C) $16,530 U D) $980 F What is the variable overhead efficiency variance for the month?


A) $15,550 U
B) $15,200 U
C) $16,530 U
D) $980 F

E) B) and D)
F) A) and B)

Correct Answer

verifed

verified

The labor efficiency variance for May is:


A) $3,978 F
B) $4,320 F
C) $4,320 U
D) $3,978 U

E) A) and D)
F) B) and C)

Correct Answer

verifed

verified

Showing 141 - 160 of 461

Related Exams

Show Answer