Consider the following work breakdown structure:  Time Estimates (days)   Activity  Precedes  Optimistic  Most Likely  Pessimistic  Start  A, B  A  C, D 445056 B  D 456075 C  E 424548 D  F 314049 E  F 273639 F  End 587082\begin{array}{l}\begin{array} { l c c c c } &&&\text { Time Estimates (days) }\\\text { Activity } & \text { Precedes } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\hline \text { Start } & \text { A, B } & - & - & - \\\text { A } & \text { C, D } & 44 & 50 & 56 \\\text { B } & \text { D } & 45 & 60 & 75 \\\text { C } & \text { E } & 42 & 45 & 48 \\\text { D } & \text { F } & 31 & 40 & 49 \\\text { E } & \text { F } & 27 & 36 & 39 \\\text { F } & \text { End } & 58 & 70 & 82\end{array}\end{array} What is the estimated expected (mean) time for activity E?


A) 35 days
B) 36 days
C) 39 days
D) 40 days
E) 45 days

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

A project consists of nine major activities, as shown below. There are three separate paths in the network: a-c-f, b-d-g, and e-h-i. (A) What is expected project duration time? (B) Determine the probability that the project will take more than 35 weeks to complete. (All times are in weeks.)  Activity  Exp. Duration  Std.Dev.  a 71 b 101 c 92 d 112 e 162 f 142 g 102 h 81 I 82\begin{array} { l l l } \text { Activity } & \text { Exp. Duration } & \text { Std.Dev. } \\\hline \text { a } & 7 & 1 \\\text { b } & 10 & 1 \\\text { c } & 9 & 2 \\\text { d } & 11 & 2 \\\text { e } & 16 & 2 \\\text { f } & 14 & 2 \\\text { g } & 10 & 2 \\\text { h } & 8 & 1 \\\text { I } & 8 & 2\end{array}  A project consists of nine major activities, as shown below. There are three separate paths in the network: a-c-f, b-d-g, and e-h-i. (A) What is expected project duration time? (B) Determine the probability that the project will take more than 35 weeks to complete. (All times are in weeks.)   \begin{array} { l l l }  \text { Activity } & \text { Exp. Duration } & \text { Std.Dev. } \\ \hline \text { a } & 7 & 1 \\ \text { b } & 10 & 1 \\ \text { c } & 9 & 2 \\ \text { d } & 11 & 2 \\ \text { e } & 16 & 2 \\ \text { f } & 14 & 2 \\ \text { g } & 10 & 2 \\ \text { h } & 8 & 1 \\ \text { I } & 8 & 2 \end{array}

Correct Answer

verifed

verified

(A) Expected duration = 32 wee...

View Answer

Which of the following is not typically treated as part of a project life cycle?


A) feasibility analysis
B) planning
C) maturity
D) incubation
E) alternative generation

F) A) and E)
G) A) and B)

Correct Answer

verifed

verified

Consider the following work breakdown structure:  Time Estimates (wks)   Start  Finish  Activity  Node  Node t0tmtp A 12112029 B 23258 C 24183042 D 3471013 E 14314043\begin{array}{r}{\text { Time Estimates (wks) }} \\\begin{array}{lccccc}& \text { Start } & \text { Finish } \\\text { Activity } & \text { Node } \quad\quad& \text { Node } \quad\quad& \mathrm{t}_{0} \quad\quad& \mathrm{t}_{\mathrm{m}} \quad& \mathrm{t}_{\mathrm{p}} \quad\\\hline \text { A } & 1 & 2 & 11 & 20 & 29 \\\text { B } & 2 & 3 & 2 & 5 & 8 \\\text { C } & 2 & 4 & 18 & 30 & 42 \\\text { D } & 3 & 4 & 7 & 10 & 13 \\\text { E } & 1 & 4 & 31 & 40 & 43\end{array}\end{array} What is the estimated slack time for activity E?


A) 0 weeks
B) 3 weeks
C) 9 weeks
D) 11 weeks
E) 12 weeks

F) A) and E)
G) D) and E)

Correct Answer

verifed

verified

Project management differs from management of more traditional activities mainly because of: (I) its limited time frame. (II) its unique, defined set of activities. (III) the requirement for use of the appropriate resources. (IV) the need for planning and execution.


A) I
B) II
C) I and II
D) I and III
E) I, II, and IV

F) B) and D)
G) C) and D)

Correct Answer

verifed

verified

In the probabilistic approach to project network analysis, the time estimate annotated tm for any activity is the:


A) mean time.
B) median time.
C) most likely time.
D) mode time.
E) marginal time.

F) B) and E)
G) D) and E)

Correct Answer

verifed

verified

Once a project is underway, the project manager usually is not responsible for effectively managing:


A) the people.
B) costs.
C) resources.
D) time.
E) project priority.

F) D) and E)
G) None of the above

Correct Answer

verifed

verified

The main function of dummy activities is to clarify relationships in network diagrams.

A) True
B) False

Correct Answer

verifed

verified

Consider the following work breakdown structure:  Start  Finish  Duration (Days)   Activity  Node  Node  Optimistic  Most Likely  Pessimistic  A 12415059 B 13546066 C 24587082 D 34324144\begin{array}{cccccc}&\text { Start }&\text { Finish }&&\text { Duration (Days) } \\\text { Activity } & \text { Node } & \text { Node } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\hline \text { A } & 1 & 2 & 41 & 50 & 59 \\\text { B } & 1 & 3 & 54 & 60 & 66 \\\text { C } & 2 & 4 & 58 & 70 & 82 \\\text { D } & 3 & 4 & 32 & 41 & 44\end{array} What is the estimated expected (mean) time for project completion?


A) 41 days
B) 70 days
C) 100 days
D) 120 days
E) 221 days

F) A) and D)
G) B) and E)

Correct Answer

verifed

verified

Activity J has a duration of 7 and an earliest finish time of 21. If J's latest start time is 16, this must mean that J's slack is:


A) 7.
B) 4.
C) 3.
D) 2.
E) 1.

F) B) and E)
G) B) and D)

Correct Answer

verifed

verified

A project is represented by the following diagram: A project is represented by the following diagram:   The expected duration of this project is: A)  12. B)  17. C)  20. D)  36. E) 77. The expected duration of this project is:


A) 12.
B) 17.
C) 20.
D) 36.
E) 77.

F) A) and B)
G) B) and E)

Correct Answer

verifed

verified

Consider the following work breakdown structure:  Activity  Precedes  Normal  Time (wks)  Crashing  Cost (1st  week) (2nd  week)  Start  A, B  A  C, D 68 B  G 456 C  E 4 D  F 566 E  H 688 F  H 6710 G  I 835 H  End 51215 I  End 65\begin{array} { l c c c c } \text { Activity } & \text { Precedes } & \begin{array} { c } \text { Normal } \\\text { Time (wks) }\end{array} & \begin{array} { c } \text { Crashing } \\\text { Cost } \left( 1 ^ { \text {st } } \right. \text { week) }\end{array} & \left( 2 ^ { \text {nd } } \right. \text { week) } \\\hline\text { Start } & \text { A, B } & - & - & - \\\text { A } & \text { C, D } & 6 & 8 & - \\\text { B } & \text { G } & 4 & 5 & 6 \\\text { C } & \text { E } & 4 & - & - \\\text { D } & \text { F } & 5 & 6 & 6 \\\text { E } & \text { H } & 6 & 8 & 8 \\\text { F } & \text { H } & 6 & 7 & 10 \\\text { G } & \text { I } & 8 & 3 & 5 \\\text { H } & \text { End } & 5 & 12 & 15 \\\text { I } & \text { End } & 6 & 5 & -\end{array} What is the total cost of reducing the project to 18 weeks?

Correct Answer

verifed

verified

Total cost...

View Answer

Some organizations use a matrix organization to integrate the activities of specialists within a functional framework.

A) True
B) False

Correct Answer

verifed

verified

In a project network, the critical path is the sequence of activities which has the:


A) most activities.
B) most nodes.
C) most events.
D) longest duration.
E) greatest variance.

F) A) and B)
G) B) and C)

Correct Answer

verifed

verified

The probability that the project will go beyond the desired time is equal to one minus the joint probability that all paths will be completed within the desired time.

A) True
B) False

Correct Answer

verifed

verified

Deterministic networks use three time estimates-shortest, most likely, and longest-for each activity in order to best determine the activity's estimated time.

A) True
B) False

Correct Answer

verifed

verified

Which of the following is not an element of the project management triangle?


A) cost
B) schedule
C) resources
D) quality
E) performance objectives

F) B) and E)
G) A) and B)

Correct Answer

verifed

verified