What is a graphical network model that depicts a project's tasks and the relationships between those tasks?


A) Gantt chart
B) PERT chart
C) Dependency
D) All of the above

E) C) and D)
F) B) and D)

Correct Answer

verifed

verified

B

What are project objectives?


A) Quantifiable criteria that must be met for the project to be considered a success
B) Products, services, or processes that are not specifically a part of the project
C) Any measurable, tangible, verifiable outcome, result or item that is produced to complete a project or part of a project
D) Defines the work that must be completed to deliver a product with the specified features and functions

E) C) and D)
F) All of the above

Correct Answer

verifed

verified

What is a project charter?


A) Specific factors that can limit options
B) Factors that are considered to be true, real, or certain without proof or demonstration
C) Quantifiable criteria that must be met for the project to be considered a success
D) A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities

E) B) and C)
F) A) and D)

Correct Answer

verifed

verified

D

What type of chart typically displays the critical path?


A) Gantt chart
B) PERT chart
C) All of the above
D) None of the above

E) A) and B)
F) B) and C)

Correct Answer

verifed

verified

Which of the following does a project manager perform?


A) Defines and develops the project plan
B) Tracks the plan to ensure all key project milestones are completed on time
C) Expert in project planning and management
D) All of the above

E) A) and D)
F) A) and C)

Correct Answer

verifed

verified

A(n) __________ chart is a simple bar chart that depicts project tasks against a calendar.

Correct Answer

verifed

verified

What is the application of knowledge, skills, tools, and techniques to project activities to meet project requirements?


A) Project management
B) Project management software
C) Scope
D) None of the above

E) All of the above
F) A) and B)

Correct Answer

verifed

verified

A

Which of the following is not a guideline for effectively dealing with change management?


A) Institute change management policies
B) Seek change
C) Anticipate change
D) Stop change

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

Identify the three primary areas a project manager must focus on managing to ensure success.

Correct Answer

verifed

verified

There are three primary areas a project ...

View Answer

In a Gantt chart tasks are listed __________ and the project's timeframe is listed ____________.


A) Vertically, horizontally
B) Horizontally, vertically
C) Vertically, Vertically
D) Horizontally, horizontally

E) B) and D)
F) B) and C)

Correct Answer

verifed

verified

An organization must identify what it wants to do and how it is going to do it. What does the "what" part of this question focus on?


A) Justification of the project
B) Definition of the project
C) Expected results of the project
D) All of the above

E) All of the above
F) None of the above

Correct Answer

verifed

verified

A(n) ____________ is a temporary endeavor undertaken to create a unique product, service, or result.

Correct Answer

verifed

verified

The PMI develops procedures and concepts necessary to support the profession of project management. Which of the following is not one of the three areas it focuses on?


A) The distinguishing characteristics of a practicing professional (ethics)
B) The content and structure of the profession's body of knowledge (standards)
C) Change in business goals during project planning (management)
D) Recognition of professional attainment (accreditation)

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

A kill switch is a trigger that enables a project manager to close the project prior to completion.

A) True
B) False

Correct Answer

verifed

verified

What are project deliverables?


A) A temporary endeavor undertaken to create a unique product or service
B) The application of knowledge, skills, tools, and techniques to project activities in order to meet or exceed stakeholder needs and expectations from a project
C) Any measurable, tangible, verifiable outcome, result, or item that is produced to complete a project or part of a project
D) Represent key dates when a certain group of activities must be performed

E) All of the above
F) B) and C)

Correct Answer

verifed

verified

A change control board (CCB) that is responsible for approving or rejecting all change requests.

A) True
B) False

Correct Answer

verifed

verified

_________ management is the application of knowledge, skills, tools, and techniques to project activities to meet project requirements.

Correct Answer

verifed

verified

A(n) _________ is a logical relationship that exists between the project tasks, or between a project task and a milestone.

Correct Answer

verifed

verified

Project ______________ are any measurable, tangible, verifiable outcome, result, or item that is produced to complete a project or part of a project.

Correct Answer

verifed

verified

Which of the following includes a common reason why change occurs?


A) A misunderstanding of the initial scope
B) Shifts in planned technology that force unexpected and significant changes to the business
C) An omission in defining initial scope
D) All of the above

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified